vault backup: 2023-09-19 07:04:24
This commit is contained in:
@@ -145,7 +145,7 @@ Progress control involves measuring actual progress against the performance targ
|
|||||||
- Authorize further work to be done
|
- Authorize further work to be done
|
||||||
An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. Tolerances are the deviation above and below a plan’s target. For example, the project should take 6 months, with a tolerance of ±1 month. Tolerance levels could also be set for all 6 tolerance areas.
|
An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. Tolerances are the deviation above and below a plan’s target. For example, the project should take 6 months, with a tolerance of ±1 month. Tolerance levels could also be set for all 6 tolerance areas.
|
||||||
# PRINCE2 processes
|
# PRINCE2 processes
|
||||||
A process is a structured set
|
A process is a structured set of activities designed to accomplish a specific objective.
|
||||||
|
|
||||||
---
|
---
|
||||||
|
|
||||||
|
|||||||
Reference in New Issue
Block a user