@@ -145,7 +145,7 @@ Progress control involves measuring actual progress against the performance targ
|
||||
- Authorize further work to be done
|
||||
An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. Tolerances are the deviation above and below a plan’s target. For example, the project should take 6 months, with a tolerance of ±1 month. Tolerance levels could also be set for all 6 tolerance areas.
|
||||
# PRINCE2 processes
|
||||
|
||||
A process is a structured set
|
||||
|
||||
---
|
||||
|
||||
|
||||