@@ -145,7 +145,7 @@ Progress control involves measuring actual progress against the performance targ
- Authorize further work to be done
An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. Tolerances are the deviation above and below a plans target. For example, the project should take 6 months, with a tolerance of ±1 month. Tolerance levels could also be set for all 6 tolerance areas.
# PRINCE2 processes
A process is a structured set of activities designed to accomplish a specific objective.
A process is a structured set of activities designed to accomplish a specific objective. A process takes one or more inputs, acts on them and delivers defined outputs. There are seven processes that offer activities to help direct, manage and deliver a project.
---