diff --git a/Notes/Literature/PRINCE2.md b/Notes/Literature/PRINCE2.md index 9ac06d1..6e7cd2b 100644 --- a/Notes/Literature/PRINCE2.md +++ b/Notes/Literature/PRINCE2.md @@ -146,6 +146,9 @@ Progress control involves measuring actual progress against the performance targ An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels. Tolerances are the deviation above and below a plan’s target. For example, the project should take 6 months, with a tolerance of ±1 month. Tolerance levels could also be set for all 6 tolerance areas. # PRINCE2 processes A process is a structured set of activities designed to accomplish a specific objective. A process takes one or more inputs, acts on them and delivers defined outputs. There are seven processes that offer activities to help direct, manage and deliver a project. +## Process 1 - [[Starting up a project]] +This process aims to prevent poor projects from starting up. The question "do we have a worthwhile and viable project?" should be asked for each project idea and documented with a [[Project brief]]. + ---